Thirty men take 20 days to complete a job working 9 hours a day.How many hour a day should 40 men work to complete the job? <br> <br>(a) 8 hrs <br>(b) 7 1/2 hrs <br>(c) 7 hrs <br>(d) 9 hrs <br> <br>Ans. (b) <br> <br>

collection of interview questions Thirty men take 20 days to complete a job working 9 hours a day.How many hour a day should 40 men work to complete the job?

(a) 8 hrs
(b) 7 1/2 hrs
(c) 7 hrs
(d) 9 hrs

Ans. (b)